Medium-voltage cabin renewed in record time

Beaulieu International Group

Ceratec was asked to renew the existing HS8 cabin at Wielsbeke’s BIG site.

The new SM6 MV cells from Schneider Electrics feed a completely new 2 500-KVA transformer. The 4 000-A busbar connected to it was in turn connected to a low-voltage distribution panel no less than 8 metres long.

The total turnaround time of this project, including preparatory work in our panel construction workshop, was just 2 weeks.